Report on QSCB Funded Project Status (as of August 1, 2011)
<br />Anticipated
<br />Lead Consultant Admin Negotiated Construction Total Project Anticipated Construction
<br />School Project Description Discipline Fees AIE Fees Budget Budget Bid Date Completion Project Status
<br />Information Technology Upgrades and New Systems
<br />Central Cabarrus High
<br />Servers, Switches, Wireless, Wiring
<br />Tech. Designer
<br />$5,500
<br />$13,293.05
<br />$256,206.95
<br />$ 275,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Concord High School
<br />Switches, Wireless, Wiring
<br />Tech. Designer
<br />$1,800
<br />$4,350.45
<br />$83,849.55
<br />$ 90,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Concord Middle School
<br />Servers, Switches, Wireless
<br />Tech. Designer
<br />$4,000
<br />$9,667.67
<br />$186,332.33
<br />$ 200,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Hickory Ridge High School
<br />Wireless
<br />Tech. Designer
<br />$500
<br />$1,208.46
<br />$23,291.54
<br />$ 25,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Jay M. Robinson High
<br />Servers, Switches, Wireless, Wiring
<br />Tech. Designer
<br />$6,000
<br />$14,501.51
<br />$279,498.49
<br />$ 300,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />J.N. Fries Middle School
<br />Servers, Switches, Wireless, Wiring
<br />Tech. Designer
<br />$3,800
<br />$9,184.29
<br />$177,015.71
<br />$ 190,000
<br />8/15/2011
<br />Mt. Pleasant High School
<br />Wireless
<br />Tech. Designer
<br />$400
<br />$966.77
<br />$18,633.23
<br />$ 20,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Mt. Pleasant Middle School
<br />Servers, Switches, Wireless, Wiring
<br />Tech. Designer
<br />$3,800
<br />$9,184.29
<br />$177,015.71
<br />$ 190,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Northwest Cabarrus High
<br />Switches, Wireless, Wiring
<br />Tech. Designer
<br />$1,000
<br />$2,416.92
<br />$46,583.08
<br />$ 50,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Northwest Cabarrus Middle
<br />Servers, Switches, Wireless, Wiring
<br />Tech. Designer
<br />$3,800
<br />$9,184.29
<br />$177,015.71
<br />$ 190,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Winecoff Elementary School
<br />Servers, Switches, Wireless, Wiring
<br />Tech. Designer
<br />$2,500
<br />$6,042.30
<br />$116,457.70
<br />$ 125,000
<br />Fall 2011
<br />12/30/2011
<br />Preliminary Design
<br />Subtotal
<br />$33,100
<br />$80,000
<br />$1,541,900
<br />$ 1,655,000
<br />TOTALS FOR ALL PROJECTS =
<br />$ 222,050
<br />Identifies projects that CCS anticipates having under contract for construction by October 15, 2011 to meet the 10% QSCB funding requirement.
<br />Identifies project budget amounts that have changed in value from the last monthly report
<br />Identifies projects that have had a change in status since the last report
<br />Prepared by: Cabarrus County Schools Facilities Management Department
<br />Attachment number 1
<br />8/1/2011