§ 3.3.1 Upon recognizing the need to perform the following Additional Services, the Architect shall notify the Owner• <br />with reasonable promptness and explain the facts and circumstances giving rise to the need. The Architect shall not <br />proceed to provide the following services until the Architect receives the Owner's written authorization: <br />.1 Services necessitated by a change in the Initial Information, previous instructions or approvals given <br />by the Owner, or a material change in the Project including, but not limited to, size, quality, <br />complexity, the Owner's schedule or budget for Cost of the Work, or procurement or delivery <br />method; <br />.2 Services necessitated by the Owner's request for extensive environmentally responsible design <br />° T bf ~ <br />alternatives, such as unique system 'a~-b ; =- '' r'" ~ ' """" °" ~ ~' '• R '• r ~~T® <br />'~~fi^~rdesigns or in depth material research (See Exhibit A for LEED Compensation.) <br />.3 Changing or editing previously prepared Instruments. of Service necessitated by the enactment or <br />revision of codes, laws or regulations or official interpretations; <br />.4 Services necessitated by decisions of the Owner not rendered in a timely manner or any other failure <br />of performance on the part of the Owner or the Owner's consultants or contractors; <br />.5 ' <br />rl, °a .. °nt~ <br />":r:.....,, <br />. rr•; <br />.8 Preparation for, and attendance at~a dispute resolution proceeding or legal proceeding, except where <br />the Architect is party thereto; <br />v T-.' 1 .. r:.. .,F r0. ; <br />.10 Consultation concerning replacement of Work resulting from fire or other cause during construction; <br />ei: <br />A r r rl. T 'r' 1 Tl TiT 1 'F rl, rr: rl, A 1.'r r <br />§ 3.3.2 To avoid delay in the Construction Phase, the Architect shall provide the following Additional Services, <br />notify the Owner with reasonable promptness, and explain the facts and circumstances giving rise to the need. If the <br />Owner subsequently determines that all or puts of those services are not required, the Owner shall give prompt <br />written notice to the Architect, and the Owner shall have no further obligation to compensate the Architect for those <br />services: <br />.1 Reviewing a Contractor's submittal out of sequence from the submittal schedule agreed to by the <br />Architect; <br />.2 Responding to the Contractor's requests for information that ue not prepued in accordance with the <br />Contract Documents or where such information is available to the Contractor from a careful study <br />and comparison of the Contract Documents, field conditions, other Owner-provided information, <br />Contractor-prepued coordination drawings, or prior Project correspondence or documentation; <br />.3 Preparing Change Orders and Construction Change Directives that require evaluation of Contractor's <br />proposals and supporting data, or the prepuation or revision of Instruments of Service; <br />.4 Evaluating an extensive number of Claims as the Initial Decision Maker; <br />.5 Evaluating substitutions proposed by the Owner or Contractor and making subsequent revisions to <br />Instruments of Service resulting therefrom; or <br />.6 To the extent the Architect's Basic Services ue affected, providing Construction Phase Services 60 <br />days after (1) the date of Substantial Completion of the Work or (2) the anticipated date of <br />Substantial Completion, identified in Initial Information, whichever is culler. <br />r •' DI C .1' rl+ 1' 'r r F.,..rh 1.°1.,.., "~~, <br />C \I71. rl. i' 'r N 1 H .i rl. A 1,'r r ..1...11 .,,,r: F.. rl.° (l.T,"°«. <br />~t- ~ <br />C--OntraEtA~ <br />7 / \ 'r r rl. 'r 1... ri.° A,•nL.:r°..t ., r tl. <br />z ~ <br />' $ir13St$nt38~y-69#~}pl8t .7 'r1. rl, .,r" ..F rl.° C...~~A.^-,u nicaics <br />'-~Trn5l3 <br />AIA Document 8201 *M - 2007 (formerly 8141 TN -1997 Part 2). Copyright m 1917, 1926, 1948, 1951, 1953, 1958, 1961, 1963, 1966, 1967, 1970, 1974, <br />1977, 1987, 1997 and 2007 by The American Institute of Architects. All rights reserved. WARNING: This AIA° Document Is protected by U.S. Gopyrigllt 9 <br />Law and International Treailes. Unauthorized reproduction or distribution of this AIA° Document, or any portion of It, may result in severe civil and <br />crimdnel penaides, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 10:21:11 on <br />06/11/2009 under Order No.1000356205_1 which expires on 7/25/2009, and is not for resale. <br />User Notes: (676254142) <br />F-1 <br />