Laserfiche WebLink
5.1.5 Applications for Payment shall indicate the percentage of completion of each portion of the <br />Work as of the end of Ihe period covered by the Application for Payment. <br /> <br />5.1.6 Subject to other provisions of the Contracl Documents, the amount of each progress pay- <br />ment shall be computed as follows: <br /> .t Take that portion of the Contract Sum properly allocable to completed Work as deter- <br /> mined by multiplying the percentage completion of each portion of the Work by the <br /> share of the Contract Sum allocated to that portion of the Work in the schedule of val- <br /> ues, less retainage of t. en percent ( 1 0 %). Pending final determi- <br /> nation of cost to the Owner of changes in the Work, amounts not in dispute shall be <br /> included as provided in Subparagraph 7.3.8 of AIA Document A2om997; <br /> .2 Add that portion of tile Contract Sum properly allocable to materials and equipment <br /> delivered and suitably stored al the site for subsequent incorporation in the completed <br /> construction (or, if approved in advance by the Owner, suitably stored off the site at a <br /> location agreed upon i,~ writing), less retainage of t. en percent ( '1 0 %); <br /> .3 Subtract the aggregate of previous payments made by the Owner; and <br /> .~ Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate <br /> for Payment as provided in Paragraph 9.5 of AI'A Document A2o1-1997. <br /> <br />5.1.7 The progress payment amount determined in accordance with Subparagraph 5a.6 shall be <br />further modified under the following circumstances: <br /> .~ Add, upon Substantial Completion of tile Work, a sum sufficient to increase the total pay- <br /> ments to the full amount of the Contract Suni, less such amounts as the Archilect shall <br /> determine for incomplete Work, retainage applicable to such work and unsettled claims; <br /> and (Subparagraph 9.8,5 of AIA Docunlent A2ot-t997 reqoires release of applicable retainage upon <br /> Substantial Completion of Work with consent of surely, if any.) <br /> .2 Add, if final completion of the Work is thereafter materially delayed through no fault of <br /> the Contractor, any additional amounts payable in accordance with Subparagraph 9ao.3 <br /> of AIA Document A2o1-1997. <br /> <br />5.1.8 Reduction or limitation of retainage, if any, shall be as follows: <br />(If it is intended, prior to Substantial Completion of the entire Work, to redoce or limit the retainage resuhing <br />from the percentages inserted in Claases ~.~.6. ~ and 5.~.6.~ above, and this is not exphdned elsewhere in the <br />Contract Documents, insert here provisions for $uch reduction or limitation.) <br /> <br />5.1.9 Except with the Owner's prior approval, the Contractor shall not make advance payments <br />to suppliers for materials or equipment which have not been delivered and stored at the site. <br /> <br />5.2 FINAL PAYMENT <br />5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made <br />by the Owner to the Contractor when: <br /> .~ the Contractor has fully performed the Contract except for the Contractor's responsibil- <br /> ity to correct Work as provided in Subparagraph 12.2.2 of AIA Document A2m-1997, and <br /> to satisfy other requirements, if any, which extend beyond final payment; and <br /> .2 a final Certificate for Payment has been issued by the Archilect. <br /> <br />WARNING: Unlk~s~l photocopylnll violates U.$, copyrtRhl I~vs and will subject the violator lo ~al pmstcutlon. <br /> <br />AIA DOCUMENT A101-1997 <br />OWNER-CONTrACTOR <br />AGREEMENT <br /> <br />The Arnerican Institute <br />of Architects <br />1735 New YorkAvenue, N.W. <br />Washington, D.C. 20OO6-5292 <br /> <br /> <br />