WATEI~ and SEWEI~ DISTRICT of cABAlql~US COUNTY <br /> <br /> ~.o. Box ?o7 <br /> (7o~) <br /> <br /> RAN DUI~t <br /> <br />TO: Charles D. MCGinnis/County Manager <br /> <br />FRO)h Walter Odell/Utilities Directo~E~ <br />DATE: July 17, lg85 <br /> <br />SUBJECT: Harrisburg Sewer Outfall Contracts 1 and 2 <br /> <br /> On July 12 and July 16, 1985, a formal inspection of the above project <br />was conducted. All line work is complete, tested, and acceptable. All <br />right-of-ways are restored and acceptable. Flow monitoring equipment on Contract <br />1 is yet to be installed. Flow monitoring equipment on Contract 2 has a defective <br />part which is to be replaced and calibrated by the manufacturer. Both contractors <br />indicated that all work should be completed within two weeks. The monitoring <br />manhole installed on the existin~ 60" outfall at the treatment plant is also <br />complete and acceptable. <br /> <br /> <br />