Kanna olis Middle School <br />PCO # 028 <br />Date: <br />06/20/17 <br />Description of Work: Add substrate board and two layers of 2.6" ISO insulation under metal roof panels <br />at clear story roofs per response to RFI # 201. This material is not specified in the documents. Time <br />component is contingent on NTP. <br />Direct Cost of Change <br />DESCRIPTION <br />I LABOR MATLI <br />EQ IPJ <br />SUBC1 <br />TOTAL <br />1,Substrate board and insulation <br />0 <br />0i <br />0 <br />10,311 <br />10,311 <br />2 <br />0 <br />0, <br />0 <br />0 <br />0 <br />3 <br />0 <br />0, <br />0 <br />0 <br />0 <br />4 <br />0 <br />01 <br />0 <br />0 <br />0 <br />5 <br />0 <br />0 <br />0 <br />0 <br />6 <br />6 <br />0 <br />0 <br />0 <br />0 <br />0 <br />7 <br />0 <br />01 <br />0 <br />0 <br />0 <br />8 <br />0 <br />0 <br />0 <br />0 <br />0 <br />9 <br />0 <br />0 <br />0 <br />0 <br />0 <br />10 <br />0 <br />0 <br />0 <br />0 <br />0 <br />11 Estimating of Change <br />20 <br />0 i <br />0 <br />0 <br />20 <br />12 Project Management of Change <br />0 <br />01 <br />0 <br />0 <br />0 <br />13 Project Administrator of Change <br />0 <br />0 <br />o <br />0 <br />0 <br />14 Scheduling of Change <br />0 <br />0 <br />0 <br />0 <br />0 <br />15 Supervision of Change <br />0 <br />0 <br />0 <br />0 <br />0 <br />16 Expendable Tools( 5% of EFI direct labor) <br />0 <br />01 <br />0 <br />0 <br />0 <br />17 Rough Hardware <br />0 <br />0 <br />0 <br />0 <br />0 <br />18 Housekeeping(1°/ of dived costs 1-10) <br />103 <br />0 <br />0 <br />0 <br />103 <br />19Dumpster(1/2%of direct costs 1-10) <br />0 <br />0 <br />52 <br />0 <br />52 <br />20 Final Clean <br />21 Record Drawings/O&M <br />0 <br />0 <br />0 <br />0 <br />0_ <br />0 <br />0 <br />0 <br />0 <br />0 <br />22 Punch List <br />0 <br />0 <br />0 <br />0 <br />0 <br />231 <br />0 <br />0 <br />0 <br />0 <br />0 <br />24 1 Overtime Adjustment <br />0 <br />0 <br />0 <br />0 <br />0 <br />251 Working Height Adjustm n-t <br />26 Congestion Adjustment <br />27 1 Out-of-Sequence Adjustment <br />01 <br />01 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />Extended Project Overhead <br />1 Supervision/Truck/Fuel <br />0 <br />01 <br />0 <br />0 <br />0 <br />2 Gen Supt/Truck/Fuel <br />0 <br />0 <br />0 <br />0 <br />0 <br />3 Project Mgr/Auto/Fuel <br />0 <br />0 <br />0 <br />0 <br />0 <br />4 Field Office/Storage <br />0 <br />0 <br />0 <br />0 <br />0 <br />5 Temp Toilets <br />0 <br />0 <br />0 <br />0 <br />0 <br />6 Temp Utilites <br />0 <br />0 <br />0 <br />0 <br />0 <br />7 <br />8 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />0 <br />SUBTOTALS »> <br />123 <br />0, <br />52 <br />10311 <br />10486 <br />42,00% PAYROLL T & 1 <br />52 <br />N/A <br />NIA <br />N/A <br />52 <br />7.25% SALES TAX <br />N/A <br />0 <br />4 <br />N/A <br />4 <br />SUBTOTALS—, <br />175 <br />0 <br />55 <br />10311 <br />10541 <br />FEE FOR CONTRACTOR-PERFORMED WORK »> <br />15.00% <br />35 <br />FEE FOR SUB-CONTRACTOR-PERFORMED WORK — <br />5.00% <br />516 <br />SUBTOTAL— <br />11091 <br />BOND PREMIUM <br />>>> <br />1.00% <br />111 <br />QUOTE >>> <br />$11,202 <br />Calender Day Time Extension Required>>> <br />Proposal expires in-16 days. <br />0 <br />This entire proposal shall become part of any future Change Order. Edison Foard reserves the right to claim and recover impact <br />costs in the event the cumulative total of Change Orders on this project is so significant to be disruptive and to cause <br />inefficiencies. This proposal is subject to review and revision if not accepted in writing within the time period stated herein. <br />Attachm <br />F-7 Page 171 <br />it number 3 \n <br />