Laserfiche WebLink
Mr. Steve tattle, Dtragar <br />FebrWry 71, 7006 <br />Page 2 <br />happened to pull the moisture up so quickly. The soil was being placed <br />correctly and the fill was placed on fabric to ensure a good sub base for fill <br />placement. There was a meeting of the Owner, WKD and Trigon to observe an <br />additional proof roll after some undercutting, rolling and compaction of the area <br />to sea if the soli could be stabilized. The lower tfiird of the parking area was in <br />poor condition. The soil pumped up and down and rutted 6 to 8 inches. The <br />conclusion by Trigon was to undercut an additional 12 inches of the soil and <br />add additional stone in compacted lifts on geogrid as a bridging device. WKD <br />asked about conducting some borings to check moisture and original sub base <br />for springs, Trigon stated that the borings would not tell the state of the original <br />subbase at this point. The stone had-been overworked and it may have pulled <br />moisture up into the fill section. This would have changed the sub base from <br />the time of the original observation. Some preliminary estimates were derived <br />on site based on the area of poor coriditions. The estimates were to cover the <br />whole parking area with geogrid to bridge the whole parking area and overlay <br />the area with a minimal of ti" stone as called for in the plans and the lower half <br />would get 18 inches of stone (12' additional stone under the original section). <br />• After discussion with Tim Lowder, WKD branch manager, about finding on the <br />site of two spring heads in the. pond area adjacent to the parking lot fill, WKD <br />posed the question to Trigon about getting borings done for underground spring <br />heads. There were several days of dry warm weather and Trigon recommended <br />digging a minimum of two test pits in the lower end of the parking fill and <br />observe if water would come up in the bottoms of the holes. <br />1.) It the water surface rose, then this should show that water was flowing <br />out of the existing ground level up through the new compacted fill which <br />softened the compaction. A possible solution could be using a French drain <br />out to daylight into the pond. <br />2.} if water didn't rise up in the holes, then this would indicate the <br />subsurface soli was in poor condition (clay soil which broke down under <br />the weight of the trucks and movement) and the water in the original soil <br />was pulled up through the new fill by wicking up in the material. If this was <br />what had occurred, then using the original estimate of geogrid and <br />additional stone would be a solution to stabilize the soil. It may also need <br />to be a combination of the two items. <br />WKD recommends due to the 5 week minimum t)me period to get finances resolved, that <br />we have the contractor temporarily seed the areas to comply with the state requirements of <br />stabilizing the area when work is stopped for 14 days and to wait until spring to doing the <br />testing which will allow the site water table in the over worked condition of the fill to settle <br />down and dry up. If it is a springhead, then it will remain wet and give a better indication <br />to use the French drains or a combination of the French drain at the bottom and additional <br />stone/geogrid in the top. The winter months will be wet, but the parking area was <br />compacted and smooth rolled to sheet water off the surface better. <br />Aker a time period of waiting, there was a week of dry weather in January and Ike's dug the <br />test pits and the pits were observed for 3 days. No water came up in the fioles. WKD and <br />Trigon discussed the need of under drain. It is a recommendation that no under drain will <br />be needed. <br />~'~~ <br />